Dear members of the Ngene team,
Thanks a lot for this opportunity to express our doubts in the use of this magnificent software.
I have been using Ngene 1 year, and I still have a doubt when it comes to the syntax. For instance, if I have the following syntax (whose priors were taken from a pilot test consisting of 3 blocks of 10 choice-sets):
Design
;alts = A*, B*, SQ
;rows = 39
;block = 3, minsum, total (10 mins), newblocking
;eff = (mnl, d)
;reject:
A.veh=0 and A.ped=0,
B.veh=0 and B.ped=0
;model:
U(A) = f[-0.00367645]*fatal[40,35,25,15,0] + v.dummy[0.06|0.2]*veh[3,2,1] + p.dummy[0.01|0.06]*ped[3,2,1] + pri[0.0015341]*price[2,5,10,15,18]/
U(B) = f*fatal + v.dummy*veh + p.dummy*ped + pri*price/
U(SQ)= asc[0.2]$
Should I be compelled to use the resulting 13 choice-sets per block or could I eliminate some of those choice-sets deliberately and reduce their quantity per block aiming to avoid the respondents’ fatigue?